t-sql - days to week and days

  • How do I convert days into weeks and days

    Ex:350 days = 50 0/7 weeks

    351 days = 50 1/7 weeks

    352 days = 50 2/2 weeks

    I have a column with days in it.How do i represent it in weeks / days in the select statement output.

  • #days / 7 = #wks

    #days % 7 = #days

    SQL DBA,SQL Server MVP(07, 08, 09) "It's a dog-eat-dog world, and I'm wearing Milk-Bone underwear." "Norm", on "Cheers". Also from "Cheers", from "Carla": "You need to know 3 things about Tortelli men: Tortelli men draw women like flies; Tortelli men treat women like flies; Tortelli men's brains are in their flies".

  • pls try below code:

    declare @days int=350

    select convert(varchar(10),(@days/7))+' '+case when (@days-((@days/7)*7))=0 then '' else convert(varchar(10),(@days-((@days/7)*7)))+'/7' end

  • I got this part.How do i concatenate both weeks and days together.

    Ex: 37 5/7 or 31 /2/7 or 41 6/7

    I have a days column

    Ex:280 days

    I would like to represent it as 40 0/7 in another column

    281 will be 40 1/7

    288 will be 41 1/7

    All this has to be part of a select statement.

    select col1,col2 ,days,weekdays from table1;

    days column will have days

    weekdays must have this information 40 0/7 , 40 0/7 , 40 0/7

    Output must be :

    Days , weekdays

    280 40 0/7

    281 40 1/7

    288 41 1/7

    How do i do this

    thanks

  • --

    --

    SELECT

    col1, col2, days,

    CAST(days / 7 AS varchar(5)) + ' ' + CAST(days % 7 AS varchar(1)) + '/7' AS weekdays

    FROM dbo.tablename

    --

    --

    SQL DBA,SQL Server MVP(07, 08, 09) "It's a dog-eat-dog world, and I'm wearing Milk-Bone underwear." "Norm", on "Cheers". Also from "Cheers", from "Carla": "You need to know 3 things about Tortelli men: Tortelli men draw women like flies; Tortelli men treat women like flies; Tortelli men's brains are in their flies".

  • sqlserver12345 (10/2/2012)


    How do I convert days into weeks and days

    Ex:350 days = 50 0/7 weeks

    351 days = 50 1/7 weeks

    352 days = 50 2/2 weeks

    I have a column with days in it.How do i represent it in weeks / days in the select statement output.

    Just double checking... you want "0 1/7" for 1 day and not "1 1/7" or "0 0/7", correct? If so, Scott's code works a treat.

    I ask mostly because the first "week" will only have 6 days. The 7th day will be "1 0/7" as currently defined.

    --Jeff Moden


    RBAR is pronounced "ree-bar" and is a "Modenism" for Row-By-Agonizing-Row.
    First step towards the paradigm shift of writing Set Based code:
    ________Stop thinking about what you want to do to a ROW... think, instead, of what you want to do to a COLUMN.

    Change is inevitable... Change for the better is not.


    Helpful Links:
    How to post code problems
    How to Post Performance Problems
    Create a Tally Function (fnTally)

  • Jeff Moden (10/3/2012)


    sqlserver12345 (10/2/2012)


    How do I convert days into weeks and days

    Ex:350 days = 50 0/7 weeks

    351 days = 50 1/7 weeks

    352 days = 50 2/2 weeks

    I have a column with days in it.How do i represent it in weeks / days in the select statement output.

    Just double checking... you want "0 1/7" for 1 day and not "1 1/7" or "0 0/7", correct? If so, Scott's code works a treat.

    I ask mostly because the first "week" will only have 6 days. The 7th day will be "1 0/7" as currently defined.

    I don't see that as the first "week" having only 6 days. The "1" full week indicates 7 days.

    6 days would result in "0 6/7", which mean 6 days of the first week, but no full week yet, i.e. less than 7 days.

    SQL DBA,SQL Server MVP(07, 08, 09) "It's a dog-eat-dog world, and I'm wearing Milk-Bone underwear." "Norm", on "Cheers". Also from "Cheers", from "Carla": "You need to know 3 things about Tortelli men: Tortelli men draw women like flies; Tortelli men treat women like flies; Tortelli men's brains are in their flies".

  • Yes.

    Just as scott has coded.

  • ScottPletcher (10/4/2012)


    Jeff Moden (10/3/2012)


    sqlserver12345 (10/2/2012)


    How do I convert days into weeks and days

    Ex:350 days = 50 0/7 weeks

    351 days = 50 1/7 weeks

    352 days = 50 2/2 weeks

    I have a column with days in it.How do i represent it in weeks / days in the select statement output.

    Just double checking... you want "0 1/7" for 1 day and not "1 1/7" or "0 0/7", correct? If so, Scott's code works a treat.

    I ask mostly because the first "week" will only have 6 days. The 7th day will be "1 0/7" as currently defined.

    I don't see that as the first "week" having only 6 days. The "1" full week indicates 7 days.

    6 days would result in "0 6/7", which mean 6 days of the first week, but no full week yet, i.e. less than 7 days.

    Yep... that's exactly what I was talking about.

    --Jeff Moden


    RBAR is pronounced "ree-bar" and is a "Modenism" for Row-By-Agonizing-Row.
    First step towards the paradigm shift of writing Set Based code:
    ________Stop thinking about what you want to do to a ROW... think, instead, of what you want to do to a COLUMN.

    Change is inevitable... Change for the better is not.


    Helpful Links:
    How to post code problems
    How to Post Performance Problems
    Create a Tally Function (fnTally)

  • sqlserver12345 (10/4/2012)


    Yes.

    Just as scott has coded.

    Agreed. Just wanted to make sure.

    --Jeff Moden


    RBAR is pronounced "ree-bar" and is a "Modenism" for Row-By-Agonizing-Row.
    First step towards the paradigm shift of writing Set Based code:
    ________Stop thinking about what you want to do to a ROW... think, instead, of what you want to do to a COLUMN.

    Change is inevitable... Change for the better is not.


    Helpful Links:
    How to post code problems
    How to Post Performance Problems
    Create a Tally Function (fnTally)

Viewing 10 posts - 1 through 9 (of 9 total)

You must be logged in to reply to this topic. Login to reply