January 4, 2013 at 8:15 am
Hi Friends,
We are going to be upgrade SQL Server 2008 R2 RTM to SQL Server 2008 R2 SP2 + CU3 on 3 servers and these 3 servers are participated in mirroring session....
Please guide me,How can i proceed this activity with getting into high risks.
---I refereed following articles (http://msdn.microsoft.com/en-us/library/bb497962(v=sql.100).aspx)
can any one explain following point much clearly
( To perform the rolling upgrade)
January 4, 2013 at 8:40 am
That link is pretty descriptive!!
As the KB says, a rolling upgrade involves upgrading the current mirror, then failing over the databases and upgrading the new mirror (which was previously the principal). Read the article a few times and you should be good to go.
-----------------------------------------------------------------------------------------------------------
"Ya can't make an omelette without breaking just a few eggs" 😉
January 4, 2013 at 9:03 am
Is it ok to upgrade mirror server when the databases are in restoring state.
Why do i need failing over the databases ?
Is this the right approach if i follow link this
1. I will start upgarding on mirror server (here dbs are in restoring state)
2. I will not do any failover
3. Start upgrading Principal server
January 4, 2013 at 10:10 am
Follow the original link, it describes exactly what you need to do!!
-----------------------------------------------------------------------------------------------------------
"Ya can't make an omelette without breaking just a few eggs" 😉