How do I schedule a job to run ONLY on weekdays?
J. Moseley
[font="Courier New"]ZenDada[/font]
mybid2003
SSCertifiable
Points: 6620
July 29, 2003 at 9:33 am
#467519
Right Click on DTS Package and select Schedule Package. Then in the Schedular, select weekly, select which weekdays would you like to have the DTS job run.
.
July 29, 2003 at 10:01 am
#467523
Thanks! Silly me, I assumed I should check daily. :o)