July 8, 2022 at 2:00 pm
Hi all,
So we are looking at our DR solution and DAG. The question is coming how the applications connect post DAG failover and the timings around the return to operation. So my question is...Post failover what the best way to get application to go to the correct (now DR) Availability group?
A few options we are discussing:
If anyone has experience of this or suggestions would be great to hear them.
Thanks,
V
July 9, 2022 at 2:10 pm
Thanks for posting your issue and hopefully someone will answer soon.
This is an automated bump to increase visibility of your question.
July 9, 2022 at 4:26 pm
DNS would be the best solution - that way you don't have to update connection strings when you failover to the DR/alternate site. Upon failover the aliases would have to be updated - maybe, depends on how DNS is setup in your environment. You would need to work with that team to determine the best options.
Jeffrey Williams
“We are all faced with a series of great opportunities brilliantly disguised as impossible situations.”
― Charles R. Swindoll
How to post questions to get better answers faster
Managing Transaction Logs
July 25, 2022 at 9:35 am
Thanks @Jeffrey Williams
Working through with the team. This was our original plan just wondered if there was any magic we could do 🙂