August 24, 2006 at 7:23 am
I am trying to get some ideas on how to calculate a rolling 4-4-5 Week Quarter. Any Ideas?
Sample Dates:
Sept= Aug 28th
Oct= Oct 2nd
Nov= Oct 30th
August 24, 2006 at 8:16 am
Try the following
select datepart(wk,'20060812')
August 24, 2006 at 8:52 am
--QuarterOfYear
Set DateFirst 6
Select (DatePart(wk, getDate())/13) + 1 as QuarterOfYear
I did this to know the Quarter of the Year I am in. I have to pass a function Today's Date (getDate()). So do I have to calculate the quarter to get the first day of the 4-4-5??
August 24, 2006 at 8:56 am
Create a function to return the quarter based on the date input
August 24, 2006 at 4:08 pm
For Fiscal Calender calculation the way I had handled was building a calender table and autopopulate it once a year (as soon as Fiscal Calender is created by finance). The reason was there could be 53 Week Year
Create table tbl_Calendar
(
dt_DOB datetime,
i_FiscalYear int,
dt_FiscalYearBegin datetime,
dt_FiscalYearEnd datetime
i_FiscalMonth int,
dt_FiscalMonthBegin datetime,
dt_FiscalMonthEnd datetime,
dt_WeekBegin datetime,
dt_WeekEnd datetime
)
Once you know the Fisacal Year Begining you can auto populate it and use it later.
Hope this helps.
Thanks
Sreejith