June 17, 2003 at 8:43 am
Hi all.
How canI change the sequence of mappings made in a transform task ?
Problem example:
Mapping 7 must now be executed after mapping 4 , mapping 6 after (7) and mapping 8 must now be done before any mapping takes place to set up DTSGlobalVariables. Mapping 7 must use GlobalVariables to do a lookup and provide a result in another DTSGlobalVariable for mapping 6 to use.
Thanks.
Graham
June 19, 2003 at 2:15 pm
Sounds a bit complex.
I'd just import the data you have straight into a staging table. Then run couple of stored procedures to update required fields in the staging table. Then insert the records into your final destination.
Hope this helps
Phill Carter
--------------------
Colt 45 - the original point and click interface
--------------------
Colt 45 - the original point and click interface
Viewing 2 posts - 1 through 1 (of 1 total)
You must be logged in to reply to this topic. Login to reply